Parand Darou Knowledge-Based Company Advances with Installation of Third 10,000-Liter Reactor in Dissolution Unit
Parand Darou Pharmaceutical Company proudly announces that during the holidays of June 2024, the third new 10,000-liter reactor for the dissolution unit was installed and commissioned with the diligent efforts of the company’s commercial and technical engineering departments. This significant achievement represents a major step towards increasing production capacity and improving manufacturing processes in the pharmaceutical industry.
Engineer Saraei, the factory manager of Parand Darou, stated: “With the commissioning of this new reactor, the production and sale of bulk opium syrup have commenced with other companies.” He added that companies such as Exir Pharmaceutical are among the interested parties for collaboration in this area. These collaborations not only help increase production but also reflect the trust of major pharmaceutical companies in the quality and production capacity of Parand Darou.
Significant Progress in Technical Infrastructure
Over the past year, Parand Darou Knowledge-Based Company has achieved remarkable successes in various infrastructural and technical areas. These advancements include increasing the raw material storage capacity, installing and commissioning new reactors, expanding centrifuge platforms, and completely replacing the steam boiler outlet valves. Other actions include relocating and reinstalling reactors, installing a 20-square-meter condenser, and stainless steel piping for 10,000-liter and 5,000-liter reactors.
Focus on Optimization and Innovation
One of Parand Darou’s main priorities is optimizing manufacturing processes and technical infrastructure. In this regard, the piping for the central line and the installation and implementation of the diesel generator panel are considered important steps to enhance the efficiency and reliability of production systems.
Recent Achievements and Development Plans
Over the past year, Parand Darou has successfully completed several major infrastructural projects that have significantly improved production capacity and operational efficiency. These projects include:
- Increased Raw Material Storage Capacity: This allows the company to store more raw materials, thereby improving responsiveness to production needs.
- Installation and Commissioning of Necessary Reactors: These reactors play a crucial role in increasing production capacity and improving manufacturing processes.
- Expansion of Centrifuge Platforms: This development enhances the company’s ability to refine and separate materials.
- Complete Replacement of Steam Boiler Outlet Valves: This action is intended to increase the safety and efficiency of steam systems.
- Relocation and Reinstallation of Reactors: This operation aids in improving the layout and efficiency of production units.
- Installation of a 20-Square-Meter Condenser: This equipment enhances cooling processes and energy efficiency.
- Stainless Steel Piping for 10,000-Liter and 5,000-Liter Reactors: These pipelines improve material flow and production process efficiency.
- Piping for Central Line: This operation enhances data transfer infrastructure.
- Installation and Commissioning of Diesel Generator: This improves reliability and stability of power supply in emergencies.
- Optimization, Renovation, and Refurbishment of Various Sections: These actions improve quality and extend the lifespan of equipment.